Building near the water in York, Maine (shoreland zoning)

York, York County · Ordinances checked 2026-10-01 · Reviewed · 10 cited sections

Allowed with board review

York's Shoreland Overlay District covers land within 250 ft of tidal waters, coastal wetlands and certain ponds, and you need a Shoreland Permit for most work there. New houses and accessory structures must be set back 100 ft from the normal high-water mark in the Resource Protection, Limited Residential and Mixed-Use subdistricts. Older buildings closer to the water can expand only within strict footprint and height caps. A vegetated buffer of 75 to 100 ft limits tree cutting and clearing.

Shoreland zoneWithin 250 ft of tidal waters, coastal wetlands and contiguous wetlands (plus listed ponds) [1]
Structure setback (Limited Residential)100 ft from the normal high-water mark (75 ft from 4-10 acre inland wetlands) [2]
Expansion within 25 ft of waterThe part of a principal structure within 25 ft can't be expanded [3]
Building entirely within 25 ftMay expand to 800 sq ft or 30% over the Jan. 1, 1989 footprint; height 15 ft or existing [10]
Expansion within 75 ftTotal footprint capped at 1,000 sq ft or 30% over the Jan. 1, 1989 footprint; height 20 ft or existing [4]
Lot coverage20% in most subdistricts; 70% Mixed Use; 30% on existing lots under 12,000 sq ft [5]
Vegetated buffer100 ft (great ponds; York River, Cape Neddick River, Brave Boat Harbor) or 75 ft (other waters) [6]
Clearing in bufferNo cleared opening over 250 sq ft; one footpath up to 6 ft wide [7]
Tree cuttingNo more than 40% of tree volume (4 in.+) in any 10 years [8]
PermitShoreland Permit required before building, expanding or changing a use [9]

Where the rules apply

The Shoreland Overlay District, shown on two Town maps, includes tidal waters, coastal wetlands and contiguous inland wetlands, plus land within 250 ft of their normal high-water mark [1]. It also covers land within 250 ft of listed ponds such as Chases Pond and York Pond. Some shoreland setbacks can reach beyond 250 ft.

Setbacks

In the Limited Residential subdistrict, all principal and accessory structures and expansions must be 100 ft from the normal high-water mark or from the upland edge of coastal wetlands and inland wetlands of 10+ acres. The setback is 75 ft from inland wetlands of 4 to 10 acres [2]. Resource Protection and Mixed Use also require 100 ft (35 ft on Harris Island). Piers, docks and other structures that need direct water access are exempt. Coastal bluffs add their own setbacks, and the height limit is 35 ft.

Expanding older buildings

The part of a principal structure within 25 ft of the water can't be expanded [3]. The exception is a building that sits entirely within 25 ft: it may grow to 800 sq ft or 30% over its January 1, 1989 footprint, whichever is greater, and 15 ft or its existing height [10]. For structures within 75 ft, the combined footprint can't exceed 1,000 sq ft or 30% more than it was on January 1, 1989, whichever is greater, and height is capped at 20 ft or the existing height [4]. Structures within the 100-ft setback get a 1,500 sq ft / 25 ft cap. Additions must go on the side away from the water, and the approved plan must be recorded at the Registry of Deeds.

Lot coverage

All structures and non-vegetated surfaces, including driveways and parking, can't exceed 20% of the shoreland part of the lot in most subdistricts, 70% in Mixed Use, or 30% on existing lots under 12,000 sq ft [5].

Trees and vegetation

A vegetated buffer must be kept within 100 ft of great ponds and of the tidal York River, Cape Neddick River and Brave Boat Harbor, and within 75 ft of other waters and wetlands [6]. In the buffer, no cleared opening can exceed 250 sq ft, and only one footpath up to 6 ft wide is allowed [7]. Selective cutting must leave a well-distributed stand, and no more than 40% of tree volume may be removed in 10 years [8]. You must submit before-and-after photos of shoreline vegetation.

Permits

You need a Shoreland Permit to build, expand, change or replace a use or structure [9]. Depending on the use, the CEO or the Planning Board issues it.

See how York compares with 8+ other Maine towns on building near the water (shoreland zoning) →

Next steps

  1. Check the Town's Shoreland Overlay District maps (Town Clerk) to see if your lot and which subdistrict it is in.
  2. Have a surveyor locate the normal high-water mark or wetland edge and measure setbacks, existing footprint and lot coverage.
  3. Take preconstruction photos of the shoreline vegetation and apply for a Shoreland Permit at the York Code Enforcement Office.
  4. For expansions of nonconforming buildings, have a Maine-licensed architect, engineer or surveyor prepare a sealed plan to record after approval.

Common questions

What is the shoreland zone in York, Maine?
The Shoreland Overlay District covers tidal waters, coastal wetlands and contiguous inland wetlands, plus land within 250 ft of them, and land within 250 ft of listed ponds such as Chases Pond and York Pond.
How far must a new building be from the water in York, Maine?
New structures must be 100 ft from the normal high-water mark in the Resource Protection, Limited Residential and Mixed Use subdistricts. The setback is 75 ft from inland wetlands of 4 to 10 acres.
Can I expand a house close to the water in York, Maine?
The part of a principal structure within 25 ft of the water can't be expanded. For structures within 75 ft, the combined footprint can't exceed 1,000 sq ft or 30% more than on January 1, 1989, whichever is greater, with height capped at 20 ft or the existing height.
Can I cut trees near the water in York, Maine?
Only within limits. No cleared opening in the buffer can exceed 250 sq ft, one footpath up to 6 ft wide is allowed, and no more than 40% of tree volume may be removed in 10 years.
Do I need a permit to build in York's Shoreland Overlay?
Yes. You need a Shoreland Permit to build, expand, change or replace a use or structure. Depending on the use, the Code Enforcement Officer or the Planning Board issues it.

Maine's shoreland zoning rules

Under the Mandatory Shoreland Zoning Act (38 M.R.S. §435–449), every town must enforce shoreland zoning at least as strict as the DEP's minimum guidelines (Chapter 1000).

What's in the shoreland zone: land within 250 ft of a great pond, river, tidal water, coastal wetland or most freshwater wetlands, and within 75 ft of a stream.

State minimum standards:

  • Setbacks for new buildings: 100 ft from great ponds classified GPA and from rivers that flow into them. 75 ft from other water bodies, tributary streams and wetlands.
  • Lot coverage: non-vegetated surfaces (buildings, driveways, etc.) are capped at 20% of the shoreland part of the lot in most districts.
  • Expanding an older building that sits too close to the water: no expansion of any part within 25 ft of the water. Within 75 ft, the total footprint is capped at 1,000 sq ft or 30% more than the footprint on Jan. 1, 1989, whichever is larger, and height at 20 ft or the existing height.
  • Vegetation buffer (within 100 ft of GPA ponds, 75 ft of other waters): no cleared opening over 250 sq ft, except one winding footpath up to 6 ft wide. Selective tree cutting only, with no more than 40% of tree volume removed in 10 years.
  • Total clearing: at most 25% of the shoreland lot area or 10,000 sq ft, whichever is larger, in most districts.

Work in or beside the water may also need a DEP permit.

State sources: 38 M.R.S. §435 (Shoreland areas) · DEP Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances · Maine DEP Shoreland Zoning program · 38 M.R.S. §480-C (NRPA permit requirement)

What the ordinance says

Exact text from York's published ordinances. Section numbers are as printed in the source.

  1. §3.8(1)(a) Shoreland Overlay District criteria, Zoning Ordinance (Revised through May 16, 2026), p. 36
    a. Tidal waters, coastal wetlands, and inland wetlands contiguous to these resources regardless of their size, and those areas within 250 feet, horizontal distance, of the normal high water mark of such resources.
  2. §8.3.11.2 Limited Residential Subdistrict, Zoning Ordinance (Revised through May 16, 2026), p. 168
    Within the Limited Residential Subdistrict, all principal and accessory structures and expansions of such structures shall set back 100 feet from the normal high water mark of any waterbody, or from the upland edge of any coastal wetland or of an inland wetland of 10 or more acres in size. For Inland Wetlands with a contiguous area of 4 or more acres but less than 10 acres, the setback shall be 75 feet.
  3. §8.3.11.4(a), Zoning Ordinance (Revised through May 16, 2026), p. 168
    a. Expansion of any portion of a principal structure within 25 feet of the normal high-water line of a water body, tributary stream, or upland edge of a wetland is prohibited, even if the expansion will not increase nonconformity with the water body, tributary stream or wetland setback requirement.
  4. §8.3.11.4(c)(1), Zoning Ordinance (Revised through May 16, 2026), p. 169
    1. For structures located less than 75 feet from the high water mark of a water body, tributary stream, or upland edge of a wetland, the maximum combined total footprint for all structures may not be expanded to a size greater than 1,000 square feet or 30% larger than the footprint that existed on January 1, 1989, whichever is greater. The maximum height of any structure may not be made greater than 20 feet or the height of the existing structure, whichever is greater.
  5. §8.1.3 Maximum Lot Coverage, Zoning Ordinance (Revised through May 16, 2026), p. 147
    a. 70% of the land area of the lot, or portion thereof, located within the Mixed Use Subdistrict; b. 20% of the land area of the lot, or portion thereof, located within any other subdistrict of the Shoreland Overlay District; or c. 30% of the land area of the lot, or portion thereof, for an existing lot of record with a total area less than 12,000 square feet.
  6. §8.3.3.2 Buffer strip, Zoning Ordinance (Revised through May 16, 2026), p. 160
    Except in areas as described in §8.3.3.1, above, and except to allow for the development of permitted uses, a buffer strip of vegetation shall be preserved within a strip of land extending: 100 feet, horizontal distance, inland from the normal high-water mark of a great pond; 100 feet, horizontal distance, from the normal high water mark of the tidal waters or upland edge of coastal wetlands along York River, Cape Neddick River, Brave Boat Harbor and their tributaries; or 75 feet, horizontal distance, from any other waterbody or the upland edge of a wetland.
  7. §8.3.3.2(b), Zoning Ordinance (Revised through May 16, 2026), p. 160
    (b) There shall be no cleared opening greater than 250 square feet in the forest canopy (or other existing woody vegetation if a forested canopy is not present) as measured from the outer limits of the tree or shrub crown. However, a single footpath not to exceed six (6) feet in width as measured between tree trunks and/or shrub stems is allowed for accessing the shoreline provided that a cleared line of sight to the water through the buffer strip is not created.
  8. §8.3.3.2(c), Zoning Ordinance (Revised through May 16, 2026), p. 161
    Notwithstanding the above provisions, no more than 40% of the total volume of trees 4 inches or more in diameter, measured at 4½ feet above ground level may be removed in any 10 year period.
  9. §18.2.1 Permits Required, Zoning Ordinance (Revised through May 16, 2026), p. 260
    No person shall engage in any activity or use of land or structure, or expand, change, or replace an existing use or structure, or renew a discontinued non-conforming use without first obtaining a Shoreland permit, when such a permit is required.
  10. §8.3.11.4(b)(1), Zoning Ordinance (Revised through May 16, 2026), p. 168
    1. The maximum total footprint for the principal structure may not be expanded to a size greater than 800 square feet or 30% larger than the footprint that existed on January 1, 1989, whichever is greater. The maximum height of the principal structure may not be made greater than 15 feet or the height of the existing structure, whichever is greater.
This page summarizes York's posted ordinances as of 2026-10-01. Ordinances are amended, and individual lots can have overlays, subdivision covenants, or HOA rules that are stricter. Confirm with Code Enforcement Department (207-363-1002) before you build. Spot an error?